Community Impact Newspaper reports on the progress of the current phase of a Central Texas Regional Mobility Authority (CTRMA) project to extend 183A Toll by 6.6 miles. The authority is adding two tolled lanes in each direction, working mainly in the existing median of US 183. “Structural and concrete work, such as retaining walls and bridges, are being built, and in 2023, work on [SH 29] to build a 30-foot-deep underpass will begin.” Construction begun in 2021 is now more than 40 percent complete and scheduled for completion in early 2025.