FDOT’s I-95 Interchange in Boca Raton Nears Finish Line (Express Lanes Cited)

Sun-Sentinel reports, “Appearances to the contrary, construction on the Interstate 95 interchange at Spanish River Boulevard in Boca Raton is 91 percent complete, according to the Florida Department of Transportation.” The report adds, “The project was originally scheduled to be completed by the fall of 2016 for $67 million but the state wanted to widen I-95 for future express toll lanes which delayed the completion date one year.”